New Fire Station, Ramsgate

Summary of works undertaken:

Foundations, Drainage, Ground Floor Slabs & External Works package to form new fire station

Duration:

35 Weeks

Main Client:

Morgan Sindall

Holiday Extras, Hythe

Summary of works undertaken:

Groundworks package to form an extension to an existing office including surface water drainage adaptions in accordance with Southern Water requirements

Duration:

16 Weeks

Main Client:

Jenner Contractors

University of Sussex, Brighton

Summary of works undertaken:

External works package to existing University

Duration:

8 Weeks

Main Client:

Willmott Dixon Interiors

Flambard Way, Godalming

Summary of works undertaken:

Externals Works package including soft & hard landscaping

Duration:

22 Weeks

Main Client:

Willmott Dixon

Royal Wells Park, Tunbridge Wells

Summary of works undertaken:

External works package to new town houses

Duration:

16 Weeks

Main Client:

Berkeley Homes

Aveley Football Club, South Ockenden

Summary of works undertaken:

Cut and Fill excercise to form new football pitches, foundations for new club house, external works throughout.

Duration:

30 Weeks

Main Client:

CBES Limited

Aberfeldy Village, Phase 2, Poplar

Summary of works undertaken:

External works and hard landscaping package to new residential development

Duration:

52 Weeks

Main Client:

Willmott Dixon

Royal Holloway University of London, Egham

Summary of works undertaken:

Full works package to form 19 blocks of student accommodation including the installation of foundations, drainage, services, external works, 10 soakaway tank installations, beam & block flooring & gas membran

Duration:

80 Weeks

Main Client:

Willmott Dixon

The Grange Care Home, Little Bookham

Summary of works undertaken:

New residential care home groundworks package including waterproof concrete basement installation, large scale underpinning excercise to retain existing facade, large external works, drainage scheme and S278 road works

Duration:

60 Weeks

Main Client:

Metnor Construction

Lynwood Care Home, Ascot

Summary of works undertaken:

New build residential care site, large reinforced concrete basement, large drainage and external works over 2 phases.

Duration:

160 Weeks

Main Client:

Willmott Partnership Homes

Victory Pier, Phase 1, Gillingham

Summary of works undertaken:

New build blocks of residential units. Paving works on pedestal to upper podium slab. External Works to existing pier arm.

Duration:

12 Weeks

Main Client:

Berkeley Homes

County Oak Retail Park, Phase 1, Crawley

Summary of works undertaken:

External Works Package to existing Retail Park including internal foundations & drainage to existing retail unit

Duration:

12 Weeks

Main Client:

RG Group

Hempstead Valley Retail Park, Gillingham

Summary of works undertaken:

Piling attendance, foundations, ground floor concrete slabs, drainage and external works.

Duration:

40 Weeks

Main Client:

Midas Retail

Haywards Heath Railway Station, Multi Storey Car Park

Summary of works undertaken:

Foundations, surface water drainage, gabion walls and tarmac works.

Duration:

42 weeks

Main Client:

Bourne Parking

Buckland Hospital, Dover

Summary of works undertaken:

Foundations, site drainage and off-site foul and surface connections, reinforced in-situ concrete frame, external works.

Duration:

70 weeks

Main Client:

Interserve

Tesco Store, Woolwich Central, South London

Summary of works undertaken:

External works and drainage for new supermarket & upper level residential facilities

Duration:

60 weeks

Main Client:

Willmott Dixon